Short answerA bathroom quote that doesn't cause rows splits labour from supply, names every item the customer is buying themselves, puts tiles in as an allowance per m², and says in writing what happens if you find rot or bad pipework at strip-out. Open the worked example below and swap in your prices.
Your Bathrooms Ltd.
Worked example: Aoife Byrne
Main bathroom, 2.4 × 2.1 m, Swords, Co. Dublin
QuoteQ-0201
| Strip out existing suite, tiles and flooring; dispose | €650.00 |
| Plumbing: first and second fix for new suite and shower | €1,400.00 |
| Electrics: extractor fan and shaver point (registered electrician) | €380.00 |
| Board and tank shower area, full waterproofing | €520.00 |
| Tiling labour, walls and floor · 18 × €55.00 | €990.00 |
| Fit customer-supplied suite (toilet, basin, vanity, shower) | €750.00 |
| Adhesive, grout, trims and sealant (supply) | €340.00 |
| ALLOWANCE: wall and floor tiles at €35/m², 18 m² (you choose) · 18 × €35.00 | €630.00 |
| PROVISIONAL: repair floor joists or pipework if found at strip-out | €450.00 |
- Subtotal
- €6,110.00
- VAT 13.5%
- €824.85
- Total
- €6,934.85
Worked example. Includes: full strip-out, plumbing, waterproofing, tiling, fitting and disposal. Customer supplies: toilet, basin, vanity unit, shower valve and screen. Please have them on site before day 3. We check them on delivery. Tile allowance: €35/m². Pick dearer tiles and only the difference is added; cheaper and it comes off. After strip-out: we send photos of anything hidden and a price before any extra work. About 8 working days. 30% deposit to book. Valid for 30 days.
Send us your next job to quote
WhatsApp the scope and your prices. We’ll send back a finished quote in your business name for you to check. First one’s free.
Allowances: the line customers misread most
If the customer hasn't picked tiles yet, don't guess and bury it in a total. Put in an allowance: a price per m² and the area. Then say in one sentence what happens if they choose dearer or cheaper ones. Only the difference changes. Customers who see "€35/m² allowance" pick tiles with a number in mind, not after the bill lands.
- Tiles: price per m² × area, plus 10% for cuts and waste on the area
- Sanitaryware you supply: a named allowance per item ("toilet up to €250")
- Taps and shower valve: allowance, or name the model you're pricing
- Say whether the allowance includes VAT. Customers assume it does
Customer-supplied items: protect yourself
Lots of customers buy their own suite online. That's fine, but write three things on the quote: the date it has to be on site, that you check it on delivery and won't fit damaged or wrong parts, and that waiting for a replacement is a new start date, not your delay. Price fitting their items as a clear labour line so they can see what they're paying for.
What happens after strip-out
You can't see under the floor until it's up. Add one provisional sum for hidden problems (rotten joists, leaking or lead pipework, a soft wall), cap it, and say you'll send photos and a price before using it. If you don't need it, it comes off. This is the single sentence that stops most bathroom disputes.
Bathroom survey checklist
Bathroom site visit
0/10Payment stages that work
- Deposit to book the date (often 20–30%), covering materials you order
- Stage payment when first fix is done and before tiling
- Balance on completion, invoiced the same day
- Extras invoiced with the balance, each one already agreed in writing