Bathroom renovation quote template

Updated 18 November 2026 · 7 min read

Tiler fitting wall tiles in a stripped-out bathroom

Short answerA bathroom quote that doesn't cause rows splits labour from supply, names every item the customer is buying themselves, puts tiles in as an allowance per m², and says in writing what happens if you find rot or bad pipework at strip-out. Open the worked example below and swap in your prices.

Worked example

Your Bathrooms Ltd.

Worked example: Aoife Byrne

Main bathroom, 2.4 × 2.1 m, Swords, Co. Dublin

QuoteQ-0201

Strip out existing suite, tiles and flooring; dispose€650.00
Plumbing: first and second fix for new suite and shower€1,400.00
Electrics: extractor fan and shaver point (registered electrician)€380.00
Board and tank shower area, full waterproofing€520.00
Tiling labour, walls and floor · 18 × €55.00€990.00
Fit customer-supplied suite (toilet, basin, vanity, shower)€750.00
Adhesive, grout, trims and sealant (supply)€340.00
ALLOWANCE: wall and floor tiles at €35/m², 18 m² (you choose) · 18 × €35.00€630.00
PROVISIONAL: repair floor joists or pipework if found at strip-out€450.00
Subtotal
€6,110.00
VAT 13.5%
€824.85
Total
€6,934.85

Worked example. Includes: full strip-out, plumbing, waterproofing, tiling, fitting and disposal. Customer supplies: toilet, basin, vanity unit, shower valve and screen. Please have them on site before day 3. We check them on delivery. Tile allowance: €35/m². Pick dearer tiles and only the difference is added; cheaper and it comes off. After strip-out: we send photos of anything hidden and a price before any extra work. About 8 working days. 30% deposit to book. Valid for 30 days.

Use the bathroom refit quote

Send us your next job to quote

WhatsApp the scope and your prices. We’ll send back a finished quote in your business name for you to check. First one’s free.

Send us your next job

Allowances: the line customers misread most

If the customer hasn't picked tiles yet, don't guess and bury it in a total. Put in an allowance: a price per m² and the area. Then say in one sentence what happens if they choose dearer or cheaper ones. Only the difference changes. Customers who see "€35/m² allowance" pick tiles with a number in mind, not after the bill lands.

  • Tiles: price per m² × area, plus 10% for cuts and waste on the area
  • Sanitaryware you supply: a named allowance per item ("toilet up to €250")
  • Taps and shower valve: allowance, or name the model you're pricing
  • Say whether the allowance includes VAT. Customers assume it does

Customer-supplied items: protect yourself

Lots of customers buy their own suite online. That's fine, but write three things on the quote: the date it has to be on site, that you check it on delivery and won't fit damaged or wrong parts, and that waiting for a replacement is a new start date, not your delay. Price fitting their items as a clear labour line so they can see what they're paying for.

What happens after strip-out

You can't see under the floor until it's up. Add one provisional sum for hidden problems (rotten joists, leaking or lead pipework, a soft wall), cap it, and say you'll send photos and a price before using it. If you don't need it, it comes off. This is the single sentence that stops most bathroom disputes.

Bathroom survey checklist

Bathroom site visit

0/10

Payment stages that work

  • Deposit to book the date (often 20–30%), covering materials you order
  • Stage payment when first fix is done and before tiling
  • Balance on completion, invoiced the same day
  • Extras invoiced with the balance, each one already agreed in writing